Sambirobyong-Pulotondo Road Repair Begins in Tulungagung, Rain-Filled Potholes Slow Early Work

Published on

spot_img

RADAR TULUNGAGUNG – Work on the long-awaited Sambirobyong-Pulotondo road repair in Tulungagung Regency began on Monday (Feb. 23), launching a major effort to restore a key alternative route ahead of the Eid travel season.

Crews started earth-filling operations from the southern end of the project in Pulotondo Village, Ngunut District. Workers deployed heavy machinery early in the morning. They also prepared stockpiles of soil, sand, and stone that trucks had delivered to the roadside a day earlier.

Overnight rain on Sunday left many potholes filled with water, slowing progress on the first day.
Ahmad Rifai Sodik, head of the Highways Division at the Tulungagung Public Works and Spatial Planning Agency (PUPR), said crews could not fill the cavities immediately.

“Work began this morning, but rain until last night left many potholes full of water. Crews must dry them first; otherwise, the results will not be optimal,” Sodik said on Monday.

Teams now drain and dry each waterlogged pothole before they begin backfilling and compaction. This extra step has extended the early-stage schedule beyond initial estimates.

The 4-kilometer Sambirobyong-Pulotondo road repair project involves a local contractor from Tulungagung. In the first phase, crews focus on closing large potholes to improve immediate safety.

Officials plan to apply a temporary asphalt layer soon after the Eid holiday period begins. They will carry out full resurfacing after Eid al-Fitr. Authorities want residents to travel safely during Lebaran, when traffic usually surges.

“The most important thing is that community activities during Lebaran can run safely. Residents often use this road as an important alternative route,” Sodik said.

Local authorities expect better weather in the coming weeks to accelerate progress. If conditions remain dry, crews can close all major potholes before the Eid exodus begins.

The Tulungagung administration previously announced that the Sambirobyong-Pulotondo rehabilitation stretches from Sambirobyong Village in Sumbergempol District to Pulotondo Village in Ngunut District. The project carries a budget of about Rp6 billion (around US$370,000) and a planned duration of four months.

Despite that timeline, the government has set an accelerated target. Officials want crews to fix the worst damage before the Lebaran homecoming season, when the route becomes a vital corridor for inter-village travel.

Latest articles

popular

Young Farmers in Tulungagung Remain Below 10 Percent as Regeneration Challenge Grows

TULUNGAGUNG - Young farmers in Tulungagung still account for less than 10 percent of the...

How should I prepare financially to launch my own business?

Far far away, behind the word mountains, far from the countries Vokalia and Consonantia,...

An entrepreneur shares 20 tips for traveling for free

Far far away, behind the word mountains, far from the countries Vokalia and Consonantia,...

Literacy Drive in Tulungagung Expands as Public Library Offers More Than 861,000 Book Collections

TULUNGAGUNG - Literacy drive efforts in Tulungagung continue to expand as the local library agency...

13th Salary for Indonesian Civil Servant Retirees Set to Be Paid in June 2026 After PMK No. 13/2026 Issued

RADAR TULUNGAGUNG - The Indonesian government has confirmed that the 13th salary for Indonesian...

More like this

BRI Blitar Ingatkan Nasabah Waspada Penipuan Investasi Imbal Hasil Tinggi

BLITAR - Nasabah BRI yang menggunakan layanan digital secara online diingatkan agar tidak mudah...

BRI Talun Dorong UMKM Naik Kelas, Fasiatin Kembangkan Usaha dan Layanan Keuangan

BLITAR - Usaha Fasiatin di Talun, Kabupaten Blitar, berkembang dari aktivitas perdagangan sembako menjadi...

Lemon Casino – Online Casino Recenzje

Lemon Casino - Online Casino Recenzje ...